A different kind of project
South Industries of Menan, Idaho is primarily known for its superior work in constructing Monolithic Domes. But in 2011, South Industries (SI) was hired to do a different kind of project.
Signal Peak Energy, co-owned by FirstEnergy Corp. and Boich Companies, asked SI to stabilize a mountain wall.
“That wall,” said SI’s president, Randy South, “was falling down on the tunnel entrances of a Signal Peak Energy coal mine near Roundup, Montana. So we sprayed the entire wall.”
Shotcreting the side of a mountain
According to Randy, that wall was 500 feet long and, in places, 40 to 50 feet high. SI stabilized it with a nine bag mix of shotcrete sprayed in place. A four-man crew worked for eight days and a five-man crew worked for the remaining two days.
Randy said, "We did it all in a two-week window — fast and furious to get it done before freezing weather came in last fall.
“Shotcrete is an incredibly efficient way to place concrete,” he added. “The same job using a forming system would have taken weeks or months. We put over 550 cubic yards right where it was needed, in a very short time.”

That wall was falling down on the tunnel entrances to a coal mine.

The wall was 500 feet long and, in places, 40 to 50 feet high.

The Signal Peak Energy coal mine is co-owned by FirstEnergy Corp. and Boich Companies.

Signal Peak Energy mine is located near Roundup, Montana.

Signal Peak Energy’s low-sulphur, Montana coal will be sent by rail to an Ohio utility company.

The South Industries crew had only a two-week window in which to shotcrete the entire wall.

They had to work fast and furious to get the project done before the winter freeze arrived.

A four-man crew worked for eight days.

Then a five-man crew worked for an additional two days.

Randy South said, “Shotcrete is an efficient way to place concrete. A forming system would have taken weeks or months. We put over 550 cubic yards of shotcrete where it was needed, in a very short time.”